Sad that this long delayed project is delayed yet again, even if its just a few months. Of course, it would be less painful if Burquitlam Station opens at Fall 2015 instead of Fall 2016.... 
I took the WCE yesterday, had to go to Coquitlam after work.
Looks like the guideway is coming along everywhere except a 100m area or so near falcon avenue. They are still leveling the grade and preparing for the base of the guideway.
Tunnel work is hard to accelerate because you generally only have one area that you can work in efficiently at a time. If there's work going on behind the TBM, it will often interfere with the excavation. Everything gets in everything else's way.
In mining, we would say that there is only one working face.
Sad that this long delayed project is delayed yet again, even if its just a few months. Of course, it would be less painful if Burquitlam Station opens at Fall 2015 instead of Fall 2016....![]()
While you're at it, maybe they could open Port Moody to Lafarge at Spring 2016 too :tup:
But how do you get the trains from Burquitlam to PoMo if the tunnel isn't ready?
I know!
Barge-Train!
In the morning, just roll the trains onto a barge at Waterfront, and float them up to PoMo, and roll them onto the tracks there.
Barge them back to Waterfront at night so the trains can get back to Edmonds for overnight maintenance.
Though realistically, there's no point in running it before it's complete, because it would entail extra costs. It would only be worth doing for some kind of photo-op/ribbon-cutting stage (which would have to be done at Burquitlam station to show it "working") and even then, it would be embarrassing to have it incomplete.
Nah...
All they would have to do take one of the Mark I train sets, and run them all 1-car on the disconnected part of the line. Maybe even run them manually if the computer system isn't setup to be able to run without the missing tunneled section. I assume it should be able to be run like that... what if there was ever a tunnel fire or collapse? I'm just thinking that it would be missing the communication infrastructure near the tunnel, so the stations closest to the tunnel would have no way for the train to "turn back."
Then for maintenance they just'd put them on a truck. That's what the TTC did AFAIK. The Port Moody station is supposed to be at-grade. The Mark I's are easier to de-couple than the Mark II's.
Though realistically, there's no point in running it before it's complete, because it would entail extra costs. It would only be worth doing for some kind of photo-op/ribbon-cutting stage (which would have to be done at Burquitlam station to show it "working") and even then, it would be embarrassing to have it incomplete.
As of yesterday, this video from BCNEWSVIDEO shows that there are 7 sections left to go on Pinetree Way.
<snip>
I drove by and noticed the gantry crane will be positioned above Glen Drive and start lifting segments sometime today. The segments are on trucks lined up along Pinetree way. This will be the last road crossing for the elevated guideway.
From Evergreen Facebook:
Shrubs in North Road median - (Coquitlam must be paying for it!)