Should be a 7000 t raft slab for the first tower stacked on that mud slab by the end of June. From a construction methods perspective, this project is almost identical to penny lane.
Looking good. How many cranes are expected on this site? Two or three?
The luffer crane up at Brookfield:
![]()
^ I'm having same issue.
I'd forgotten how big the parkade is.
With all the buildings of different heights and widths on the 7th Ave side, it wasn't easy to get a proper idea of just how gargantuan the parkade actually is.
With the webcam 'birds-eye view' it easily shows that it takes up almost half the block.
whew!
Any guess on when the underbelly for this beast will be at grade?
This building will have an approximate 2000 tonne raft slab, poured around the 3rd week of June. Still a lot of excavation to take place before the outline of the building will be seen. Second crane in a couple of weeks.