I decided to look it up myself:
Parry Sound to Nobel - Completed and opened 2010
Nobel to Highway 522 - In negotiations with First Nations
Cranberry to Alban - Construction to begin in 2014, opening 2016?
Alban to south of Highway 637 - Construction underway, opening 2015?
Highway 637 to Estaire - Completed and opened 2012
Estaire to Richard Lake - Completed and opened 2008
Richard Lake to Highway 17 - In development and planning, likely to be constructed concurrent with twinning the Sudbury Bypass
I agree that 2017 is not going to happen. I'm thinking around 2021 or so is reasonable, depending on when the First Nations issues are solved. The section through the Wahta territory (south of MacTier) was not completed until 2008, despite surrounding sections being opened much sooner:
* Through the 1980s it was built from Barrie to Coldwater, in multiple stages, with the last section opening in 1988.
* Waubaushene to Port Severn - opened 1991 (before then, 400 ended at 12)
* Port Severn to Crooked Bay - opened 1996
* Crooked Bay to Gibson Lake - opened 1997
* Gibson Lake to Musquash River - opened 1999 (but was not a freeway until 2005)
* Wahta Territory - opened 2008
* MacTier to Horseshoe Lake - opened 2003
* Horseshoe Lake to edge of Parry Sound - opened 2001
* Parry Sound Bypass twinning - opened 2007