The pace of construction on 1WTC seems to have slowed slightly. Normally they were doing 2 floors in exactly 2 weeks, starting on a Monday and ending at the end of the following Saturday workday. By this pace, they should have finished the last 2 floors by the end of last Saturday, yet they were still installing the floor beams and the metal decking until about Thursday of this week. Also, now that they've finally started on the next two floors (only this morning), they're only installing the perimeter columns instead of the core columns. When they do this, it usually means the pouring of the concrete in the core is slowing them down... which wouldn't be surprising, considering that we're now entering winter, which I'm sure slows things down with the concrete due to the temp and only being able to pour on warms days, or having to install those huge warmers around the entire core.