These are construction drawings for the NCC's
Portage Bridge Quebec Shoreline (PBQS) Rehabilitation – Pathway & Shoreline Works, NCC project
337-07.
The drawings are marked
"Issued for Construction".
Here's a summary of what the project actually involves.
High-level overview
The project is essentially rebuilding the waterfront strip
immediately west of the Portage Bridge on the Gatineau/Zibi side of the Ottawa River.
There are three major components:
- Rebuild and improve the multi-use pathway along the river.
- Stabilize the riverbank with a substantial new retaining wall and rock/riprap erosion protection.
- Landscape and furnish the corridor with trees and other planting, benches, railings, lighting/electrical work, drainage, pavement markings, etc.
So this is considerably more than simply repaving the existing pathway.
The finished corridor should essentially be:
new asphalt pathway → landscaped edge → railing/retaining structure → stabilized rocky shoreline → Ottawa River
The work appears to extend roughly
250–300 metres west from Portage Bridge, toward the Zibi lands/zip-line area.
1. Reconstructed multi-use pathway
The existing riverside pathway is being substantially reconstructed.
The drawings show:
- new asphalt pavement
- new granular/base construction
- pathway regrading
- drainage improvements
- edge treatments
- new pavement markings
- solid yellow centre line in portions
- white line in portions
- StreetBond/limestone-coloured pavement treatment in some locations
The pathway elevations and surrounding terrain are carefully graded so that runoff is controlled rather than simply flowing down and eroding the riverbank.
2. Major new retaining wall
This looks like one of the biggest engineering components of the project.
A
new retaining wall will follow the river side of the pathway for a substantial distance.
It isn't simply a conventional poured concrete wall. The drawings show a
segmental/block retaining-wall system made from large concrete blocks.
The structural system includes:
- multiple courses of large concrete blocks
- staggered block joints
- geogrid reinforcement extending back into the soil
- engineered backfill
- clear drainage stone
- a 150 mm perforated drain behind the wall
- non-woven geotextile
- special block arrangements at each end of the wall
The geogrid is important: long layers of reinforcement extend horizontally back into the earth, effectively tying the soil and retaining wall together into one reinforced structure.
3. Shoreline stabilization / armour stone
A major purpose of the project is clearly
erosion control.
The riverbank below and around the retaining wall will be reconstructed using large amounts of
riprap / armour stone.
Work includes:
- excavating and regrading portions of the existing bank
- installing large armour stone
- installing smaller rock/filter material underneath where required
- geotextile/filter layers
- repairing existing erosion
- reshaping the transitions into the existing shoreline
- tying the new work into the existing bank at both ends
There are even notes allowing additional excavation and riprap where necessary to achieve the required shoreline slope.
So although the pathway is the most visible part of the project,
shoreline stabilization appears to be one of its main engineering purposes.
4. Drainage
There is an entire civil drawing dedicated to drainage.
Both surface water and groundwater have to be managed around the new path and retaining wall.
In particular, the retaining-wall detail includes a
150 mm perforated drain surrounded by clear stone behind the wall.
This allows groundwater to escape rather than accumulating behind the retaining structure and creating hydrostatic pressure.
The pathway and surrounding ground are also carefully graded to control surface runoff.
5. Landscaping
There's also a surprisingly substantial landscaping component.
The landscape plans show:
- new trees
- shrubs
- perennials
- grasses
- new planting beds
- soil preparation
- protection of some existing vegetation
- restoration of areas disturbed during construction
Some of the vegetation is integrated into the rocky shoreline rather than simply creating a manicured lawn.
The result therefore seems intended to have a relatively
naturalized riverfront appearance, despite the substantial engineering underneath it.
6. Benches and small rest/viewing areas
Several small widened areas appear alongside the pathway.
These incorporate things such as:
- benches
- paved/concrete pads
- landscaping
- other pathway furniture
So the corridor is intended not only as a cycling/walking connection but also as a small
waterfront public space where people can stop and sit by the river.
7. New railings
The drawings contain extensive references to new
railings / garde-corps.
These appear primarily where the pathway sits above the retaining wall/shoreline and fall protection is required.
Interestingly, the structural drawings coordinate the retaining-wall construction with the railing foundations.
There is even a note requiring the contractor to lay out the exact beginning of the retaining wall in the field while accounting for existing and proposed railing footings.
So the railing is structurally integrated into the shoreline work rather than simply being added afterward.
8. Electrical / pathway lighting
There is a meaningful electrical component, apparently associated primarily with
site/pathway lighting and related infrastructure.
9. Zibi / zip-line area
The drawings clearly identify:
- Zibi Lands
- Ottawa River
- Portage Bridge
- Zibi Zip Line Landing Facility
The new pathway and shoreline work run through this area, and some of the construction has to be coordinated with the existing zip-line landing facility.
In other words, this is essentially an upgrade of the
NCC waterfront corridor immediately west of Portage Bridge and alongside the Zibi development.
What all these drawings are showing
A lot of the drawings look almost identical at first because several engineering disciplines are drawing the same stretch of shoreline for different purposes.
TL;DR
Despite the project name making it sound somewhat like a pathway upgrade, this is really a
fairly substantial shoreline rehabilitation project.
The existing riverside path and eroding/irregular shoreline west of Portage Bridge are being replaced/reworked into a much more engineered waterfront corridor:
reconstructed paved multi-use path + landscaping + benches + railings + retaining wall + drainage + armour-stone shoreline stabilization + lighting/electrical work.
When finished, it should look much more like a deliberately constructed
waterfront promenade/pathway, while underneath it is a fairly serious retaining-wall and erosion-control system.