Regina Construction IV


Data center video from a guy on Facebook with a Mavic 3. Judging from the size of downtown in the background he's using the 7x optical zoom (maybe not, part way through the video he switches to a higher zoom so might have started at 3x and switched to 7x). https://www.facebook.com/reel/1675510957051781

I'd love one of those but they are about $3500 of the Mavic 3 which is the previous generation, and $4500 for the current Mavic 4. Though the 7x camera has the smallest / least sensitive sensor of the 3 cameras on the drone. The Air3s is half the price and does much of what the Mavic can do. 4K / 12MP photos with a 1" sensor vs 6K / 20MP 4/3" sensor and doesn't have a variable aperature camera.
 
Last edited:
Douglas Park project moving slowly (it has been wet), but they have poured the first section of foundation wall and removed the forms. Arens road ready to be paved. BMX track paved, should be ready to open soon if they landscape around it with sod. I took the gravel route from Wascana View to Wascana Parkway so I got some data centre photos while I was there.

BMX track video.
https://www.youtube.com/watch?v=LUiX4BnGNeQ

https://www.flickr.com/photos/reginaconstruction/

55378103572_38265e8e39_z.jpg
55379437840_17282df748_z.jpg


55379167478_d7827b319c_z.jpg
55379039771_0cdd5ea1de_z.jpg


Data centre album: https://www.flickr.com/gp/reginaconstruction/E69Y4799Bw
 
Douglas Park project moving slowly (it has been wet), but they have poured the first section of foundation wall and removed the forms. Arens road ready to be paved. BMX track paved, should be ready to open soon if they landscape around it with sod. I took the gravel route from Wascana View to Wascana Parkway so I got some data centre photos while I was there.

BMX track video.
https://www.youtube.com/watch?v=LUiX4BnGNeQ

https://www.flickr.com/photos/reginaconstruction/

55378103572_38265e8e39_z.jpg
55379437840_17282df748_z.jpg


55379167478_d7827b319c_z.jpg
55379039771_0cdd5ea1de_z.jpg


Data centre album: https://www.flickr.com/gp/reginaconstruction/E69Y4799Bw

Once again, thank you so much for these photos! You're really doing great work, and it's very much appreciated!
 
Boom lifts delivered for the Costco building assembly. Looks like they are getting close to finishing the site drainage installation. The orange excavators have been all over the site the past month or so installing pipes to connect to the storm water storage. More gravel delivered in the past few days so they should finish up the storm water chambers soon with a dry stretch in the forecast.

I think this building on the east side of Westerra was about to start. https://www.regina.ca/export/sites/...lopment/PL202500394-8101-Dewdney-Avenue-2.pdf

Looks like the demolition part of the bypass bridge repair is done. Resting pads for the new girder have been poured.

https://www.flickr.com/photos/reginaconstruction/

55380930043_8638ac0988_z.jpg
55380930183_09dc3d8312_z.jpg


55380983029_85a920fdba_z.jpg
55380930348_f6013f0b78_z.jpg
 
"Rapid" housing project update. https://www.ctvnews.ca/regina/artic...ousing-project-transferred-to-city-of-regina/


Also the 2026 aerial imagery is available on the pain in the ass to use site (can only zoom out so far, and images don't always fully load, it goes nuts if you pan outsite the allowed area forcing you to reload). Its usually a few months until the overhead mosaic gets loaded onto the regular aerial imagery viewer. Pictures were taking between May 24 and June 14. The data center is outside the coverage area.

https://opengis.regina.ca/PictometryIPA/ReginaIPA.aspx?lat=50.443904&lon=-104.604772
 
Last edited:
Starting to prepare a few areas at the Costco for paving. Not sure if they'll pave right away or if they just want flat areas to store materials and run the boom lifts for building construction. Covered more of the storm chambers with dirt. Overnight ring road restrictions starting Monday evening to do the north Albert bridge deck concrete.

Two panoramas at the Grand Coulee Truckstop. I just noticed in those panoramas there are tube forms for the above ground portion of the light pole and large sign bases.
https://cdn.pannellum.org/2.5/panne...flickr.com/65535/55384426276_378f3d4115_o.jpg
https://cdn.pannellum.org/2.5/panne...flickr.com/65535/55384426251_5192acfb2c_o.jpg

https://www.flickr.com/photos/reginaconstruction/

55384827925_7f7631efb4_z.jpg
55384827930_627ba67dd3_z.jpg


55384425806_d55eb50e02_z.jpg
55383498157_38c8972207_z.jpg
 
Last edited:
Drove by Costco this am. I was surprised at how extremely active the site was given it is at a similar stage to the Bell Data Centre and several smaller projects. Lots of work out there for earth movers, concrete companies and pavers.
 
Installing some precast panels at the Costco. Should be just for the loading bay judging from the city's 2018 aerial photos that showed the east Costco partially constructed. Even the taller section of wall they are forming up is the same as the east store.

55386338593_0427abfb96_z.jpg


APDHNGpl.jpeg


Might have to manually select 2018 on the viewer and can change camera angles using the circle in the upper left.
https://opengis.regina.ca/PictometryIPA/ReginaIPA.aspx?lat=50.443508&lon=-104.507563
 
Curb machine near Courtney to do the curbs for the Rink extension into Coopertown. Starting to install storm drains in what I think is the last road for phase 1. Piles going in for the McDonalds already. First layer of pavement on Arens, I think they are setting the manhole / water valve heights now. Doing the finishing touches on the BMX track. Second pile driller at the Grasswood apartment project, and a retaining wall started for a second building. Maybe they are going to do all the buildings at once.

Constant stream of trucks hauling dirt out to the data centre site for a couple more building pads. Got some photos / videos of the #6 dirt hole this afternoon. When I was bringing the drone in to land I looked up and was like "that's not my drone!" There was also a much larger octocopter out there. I had see its shadow towards the end of the video I recorded but from the controller screen I thought it might have been a bird. I managed to keep the turns pretty smooth in the video but there were a few spots I slightly jerky. I always keep forgetting to lock the video settings before pressing record, in auto the exposure changes as clouds pass.

Dirt pit video: https://www.youtube.com/watch?v=KEEhE27v1fs

Panoramas (Coopertown, Rosewood, Eastbrook BMX track)
https://cdn.pannellum.org/2.5/panne...flickr.com/65535/55387034086_e6eae2b144_o.jpg
https://cdn.pannellum.org/2.5/panne...flickr.com/65535/55387431365_c2af5a039c_o.jpg
https://cdn.pannellum.org/2.5/panne...flickr.com/65535/55387034666_57b73ac975_o.jpg

https://www.flickr.com/photos/reginaconstruction/

55387033766_cde67e015e_z.jpg
55387221074_068f90b39f_z.jpg


55387034071_8a4633a28e_z.jpg
55387034156_a769ff0898_z.jpg


55386100947_b19c7889c6_z.jpg
55387221654_73af93a6d5_z.jpg


55387432570_4d7585d21f_z.jpg
55387167488_3cce2593dd_z.jpg


Data Centre Album: https://www.flickr.com/gp/reginaconstruction/c8R21M296J

55387034571_99a7a8de15_z.jpg
55387222089_5834c53d6a_z.jpg


55386375932_ff4c89eba1_z.jpg
55387307816_2569c8817a_z.jpg
 
Last edited:
I was surprised at the change at the Costco site since yesterday. Deliveries of steel columns, beams and trusses. A triangular section they'd been prepping has been paved. About half the remaining storm chambers placed. Compacting of the SW corner of the site, presumably the next section to be prepped for pavement.

I stopped there before going over to the north Albert bridge. I got there a bit too early since I wanted to stop at the Costco while there was still plenty of light. I went back later for video and some pictures.

https://www.youtube.com/watch?v=mvfIXRIXWcE
Second video I edited this morning, focus is a bit off which seems to happen a lot in the dark with the 2x zoom mode. https://www.youtube.com/watch?v=t7eNA2uRVIg

A Costco panorama before the storm chambers are covered. https://cdn.pannellum.org/2.5/panne...flickr.com/65535/55391193242_19747e1703_o.jpg

https://www.flickr.com/photos/reginaconstruction/

55392309304_0783864d00_z.jpg
55392308929_d7ec88636d_z.jpg


55392524810_f839fd0417_z.jpg
55392129291_8b1868341d_z.jpg


55391327187_7eb2e4267a_z.jpg
55391327247_d5b3b787e9_z.jpg
 
Last edited:
Tender posted for an engineering consultant for Taylor Field redevelopment. No pictures other than one showing site boundaries.
 
I saw a full depth reclaimation machine (looks like a piece of farm equipment with big tires) at the Costco site and was wonder what they were using it for. Looking at photos from today I caught it moving away from the SW corner of the site where it had been working. Its tire tracks in disturbed soil. Its working in conjunciton with the compactors over there. They are used to stabilize soft soils so they don't collapse under weight, so there must have been a soft spot over there. Its like a giant carbide rototiller that can inject water and either lime or cement into the soil.

They added a construciton trailer, containers, more boom lifts and materials to the part that was paved yesterday. Most of the remaining interior column bases have forms added since yesterday.

Work progressing at the Douglas Park project, the pile driller is gone and foundation wall extended since I was last there. Arens Road paving is done (but not open). Maka Park had its grand opening on Sunday and was busy today. I took a zoomed in video of the pump track and one of the park.

Ended up taking a lot of data centre photos since the thin overcast made for good lighting. Were doing a concrete slab pour out there tonight. Putting the top layer on another building pad, also some building parts stored on it. Might be close to the end of dirt hauling as they are running out of space on the site.

The drone is definitely having trouble keeping the camera level. Its more noticeable taking photos at the data centre since the angle often has the horizon showing. How much it is off level depends which direction the drone is facing, probably an issue with a gyroscope in the IMU. I'll probably just live with it for a while since I'd rather not have it gone for over a week again right away.

Pump track: https://www.youtube.com/watch?v=gQCtBjX5UnM
Maka Park: https://www.youtube.com/watch?v=VQBedkKpKRU

https://www.flickr.com/photos/reginaconstruction/

55394564508_b491a1d24a_z.jpg
55393498362_9dc4477885_z.jpg


55394618424_800d697834_z.jpg
55394564733_e7afd00004_z.jpg


Data centre album: https://www.flickr.com/gp/reginaconstruction/4T4nkQ4p00

55393498712_965f16ef77_z.jpg
55393498802_f77911553c_z.jpg
 
Last edited:
I saw a full depth reclaimation machine (looks like a piece of farm equipment with big tires) at the Costco site and was wonder what they were using it for. Looking at photos from today I caught it moving away from the SW corner of the site where it had been working. Its tire tracks in disturbed soil. Its working in conjunciton with the compactors over there. They are used to stabilize soft soils so they don't collapse under weight, so there must have been a soft spot over there. Its like a giant carbide rototiller that can inject water and either lime or cement into the soil.

They added a construciton trailer, containers, more boom lifts and materials to the part that was paved yesterday. Most of the remaining interior column bases have forms added since yesterday.


https://www.flickr.com/photos/reginaconstruction/

55393498362_9dc4477885_z.jpg

Do we know if Canola Ave is getting extended west to Pinkie as part of & to align with the opening of Costco?
 
Do we know if Canola Ave is getting extended west to Pinkie as part of & to align with the opening of Costco?

The site plan shows parking in that area, so they aren't adding an access there. I checked the current neighbourhood plan and it shows a Pinkie entrance on Wasacase blvd which is just south of Wheat Crescent. But the part of Wascase to get to Pinkie isn't part of the current construction. But but there has been a dirt track there that people use as a shortcut. It had been blocked before current construction but people have a habit of detouring the blockage.

https://www.westerraregina.ca/builders
 
Last edited:
Its a good thing the Costco is close for how often I stop to take pictures, 347 in the album already. The steel started going up today. Some of the storm chambers extended to the end, so they'll all be covered up in a few days. In the last picture there are a bunch of tension rods being assembled, a fork on each end and turn buckle in the middle.

Moving fast installing pipes along the last crescent in Coopertown.

Two cranes up at the bypass bridge, new beam should be lifted in the next day or two though I didn't see it on site. (on a whim I decided to check the highway hotline page and there is a construction note that the bridge will be closed for 20 minutes between 7:00 and 8:00 am on Thursday. with that short of window I should be able to get out there while they are doing it)

https://www.flickr.com/photos/reginaconstruction/

55396767504_1f9e1b38a9_z.jpg
55396977360_b821711d29_z.jpg


55396977390_2d4b1e3bc7_z.jpg
55395649232_0a75a2fa8c_z.jpg


55396589931_9fd390bdd5_z.jpg
55396590016_4da0a02a28_z.jpg


55396718268_f61b96178c_z.jpg
55395649622_589830d8ea_z.jpg
 
Last edited:
New girder same as the old girder. Staking out the site waiting for the lift. I don't use the drone to phone transfer option much. Cranes not up yet road needs to be closed before lift off trailer.



 