Also i'm not sure why they keep saying 4 months.
Broadway and main is one of the many stations. How are they planning to do the same thing everywhere else?
Broadway (meaning full accessibility to the whole street) will close for almost 2 years. I don't see how could be any different. Assuming an average of 4 months for every station.
Unless they give up and use the 1-lane closure for the next stations and then we are looking at 3-4 years of partial closure. But it's unlikely.
4 months is how long it's supposed to take each station where they rebuild the street like this, and they're doing the stations sequentially.
Which means the entire stretch is going to take a little more than a year (it's 5 stations on Broadway in total (people seem to forget that Arbutus also has to undergo the same rebuilding))
So we're looking at rolling 4 month closures running all the way up until late Spring of next year.
A year from now they should be at Granville station before they start the final stretch at Arbutus 4 months later to be done completely by early to mid-summer.
Just in time before the line is scheduled to open in the Fall.
I'm suspecting they gave themselves some elbow room with those 4 month estimates and it will take less time than that (like 3 rather than 4 months).
So it wouldn't surprise me if they're done by Spring next year instead.
I actually think they should have bitten the bullet and done them 2 stations at a time.
Bear the pain of it all and be done with everything before the end of the year.
Granted, they most likely deemed that such a strategy might have been (even) more costly to Broadway businesses on a broader scale.