I seriously didn't recognize 99 King with the lighting in that photo hiding the two-tone look. Agree the windows leave a lot to be desired. You don't suppose they are opening because central AC has been deleted to cut costs? I can't imagine doing that in 2025 but who knows?:shrug:
Some of the older hi rise condos in Vancouver (15-20 years old and up) don't have air and without buying a portable 10,000 BTU AC and jury rigging the exhaust hose they are virtually uninhabitable in the summer.
So it’s not going to have any sort of central heating or cooling? Will there not be heat pumps attached all over the side of the building if there’s no central AC?
It’s true you don’t really need air conditioning in Saint John, but it’s nice to at least have a heat pump.
I have no idea but I can't imagine individual heat pumps without balconies. How would you access for service?
I'm dubious until there's shovels in the ground, but everyone I know who golfs is resolute that the city could sustain another course. Gotta wonder about landfill proximity causing unpleasant aromas.
In this area, it would be great to see twinning as far as the Colonel Nase exit and a reconfiguration of the 7/177/Crane Mountain interchange, especially if some of Acamac Backland is going to get upgraded. I don't think there's a place in the province where 'RIGHT LANE ENDS' means so little to so many, as Route 7 northbound, and beyond Colonel Nase, there's not really a need for full twinning. This section does get congested more than people would realize.
You'd only need two new overpasses (over Route 177 and Henderson Lake Road) and the land is all DTI property. Less than three miles total. Make the northern terminus right-lane-exit onto Colonel Nase.
I can't see this being excessively expensive.
Bringing this up from a couple pages back as I'm here for the first time in years, but -
Living in Westfield, I've never understood why they didn't do the same thing with the existing Grand Bay interchange and simply have the right lane exit. The narrowing just before an exit causes all kinds of traffic headaches as nervous or incompetent drivers slow down in the only through-traffic lane well in advance of the off ramp.
Personally I'd love to see the twinning of the highway carried all the way through to the Welsford bypass, so we'd have a contiguous four-lane highway from Route 1 to the other side of Welsford where there is a much better engineered transition to two lanes. That would be more than sufficient, as there is really no need for Route 7 to be fully twinned. At most it could maybe do with another passing lane here and there, but it already has quite a few.
Some big new NB Power electrical infrastructure projects planned:
Obviously this is great, but I feel the city should politely demand some Moncton-like paths along these lines as part of the approvals process, particularly from the Boars Head/Millidge intersection to Crystal Lake trail, about 3 km. Maybe get them to buy the southeastern part of Green Head and turn it over to Dominion Park too.
- New transformer at Coleson Cove
- 37 km of new transmission lines (double 138 kV on new towers) from Coleson Cove to Glen Falls, mostly following the existing route over Green Head and through Rockwood
- A new 4.6 km tap line to the pulp mill financed by JDI
New permits registered yesterday, (Jan.27th 2026), for the NB Museum at 277 Douglas Avenue. "Phase 1 - foundation for addition". Valued at $7,325,000.
New permits registered yesterday, (Jan.27th 2026), for the NB Museum at 277 Douglas Avenue. "Phase 1 - foundation for addition". Valued at $7,325,000.
New permits registered yesterday, (Jan.27th 2026), for the NB Museum at 277 Douglas Avenue. "Phase 1 - foundation for addition". Valued at $7,325,000.
I seriously hope they would consider a path connecting Millidgeville to Rockwood before a hypothetical future neighbourhood, especially since work is going on already. A crushed gravel path wouldn't be a big deal at all from a complexity or cost perspective. It doesn't need to be Harbour Passage 2.
Welcome to Cardinal Suites, a modern apartment and townhouse community by PMG Living in Saint John, New Brunswick.
Cardinal Suites is a growing residential development made up of multiple phases, offering thoughtfully designed homes in a connected community.
• 15 Blue Jay Way — move-in ready!
• 35 Blue Jay Way — Ready by October 2026
• Cardinal Suites Townhouses — coming approximately Fall 2027
We’re excited to start sharing more about the community, available suites, and upcoming phases as Cardinal Suites continues to take shape.