Quote:
Originally Posted by Dengler Avenue
Something’s just occurred to me: what’s the slope profile of Perimeter Highway right now?
Back in the days, some roads were built with 0% slope on flat terrain. (Even MTO did that.) Nowadays, that’s a big no-no especially in floodprone area like Winnipeg.
If M.T.I. has to redo the slopes (from 0% to 0.5%), that will definitely add to the cost.
Admittedly my tone came off arrogant in an earlier post. My point is that there are more than what meets the eyes when it comes to accounting for ground condition.
|
Most of the roadwork is greenfield new construction, so the slope profile should be modernized regardless of current status. I don't know what standards the old segments were built to.
As for cost:
Using Biff's estimate and round up, let's assume the bridge portion costs 60 million. That's still 175 million left for ~3 km of new 4 lane road, ~3 km of new PTH 3, and a handful of reroutes of residential grade local roads, collectors, and service roads.
The utilities relocation is probably on par to what had to move for the St Mary's interchange.
The real distinction between St Mary's and this project - as others have pointed out - is the amount of land acquisition required. Prime farmland that would have been urbanized into Oak Bluff eventually, so the fair market value was probably quite high. Adding to this, there was an article saying the way the parcels of farmland were being chopped up would make it challenging or impossible to farm them, so some landowners may have negotiated a heftier payout.
https://www.ctvnews.ca/winnipeg/article/...-expropriation-over-interchange-project/