I noticed the McGillivray Interchange project section was updated on the MTI website. Timelines align with what's been discussed here. Construction start in 2026.
https://www.gov.mb.ca/mti/hpd/pth100/index.html
Timeline
June 2021 McGillivray Boulevard Interchange Project Announced
May 2023 Contract awarded to WSP Canada Inc. for Owner's Engineer Work
December 2023 Complete Interim Phase – Phase 1 – Project Preparation/Confirmation of Project Plan
February 2024 Stage 2 Engagement: Refined roadway and structure design presented and collect feedback collected
2024-2025 Procurement of Design Build Contract, from Request for Proposal Qualification (RFPQ) stage to Request for Proposal (RFP) stage
Late 2025 Award of the Design Build Contract
2026-2029 Detailed Design and Construction
Fall 2029 Traffic Availability Target Date
Summer 2030 Construction Completion
There's also a set of drawing which I'm not sure I've seen. They're from summer 2024. Nothing new really. But shows the project layout.
https://www.gov.mb.ca/mti/hpd/pth10..._refined_functional_design_roadworks_plan.pdf
Should be awarded any time now.