Not sure if this is news, Daily Hive is quoting MOTT that it will be open to traffic by Christmas. That's pretty much been the plan since the delayed schedule was announced last year, to be open by the end of Fall 2025.
Recalling that article, I don't think it explicitly said Christmas 2025, did it?
“It’ll be open before Christmas,” [Farnworth] said.
As the minister and Premier David Eby walked away from the media scrum, a joking aside from Eby to Farnworth was caught on a hot mic.
“Glad you didn’t say which year,” Eby said.
https://globalnews.ca/news/11405103/pattullo-hot-mic-eby-joke/
I wish there was a polymarket to make bets on whether the bridge opens in 2025 or not. Their timeline has 0 credibility. Just a few months ago they said they will finish connecting the bridge in summer....now its moved to October. January 2026 is my bet for when the bridge opens.
Zero electrical work or drainage work has been done. Another 4-6 weeks to join the bridge deck and you anticipate more delays due to weather.
They might do something stupid where they are sloppy as fuck and open it up to NB only traffic while they continue to do periodic lane closures to redo a ton of work and continue construction through 2026 and 2027.
They need to rip out part of the existing bridge approach to allow completion of the new approach and road tie in.Why would northbound traffic be open before southbound?
They need to rip out part of the existing bridge approach to allow completion of the new approach and road tie in.
This has always been the plan and is fairly standard practice, not something "sloppy as fuck" as the troll above posted.
Webcam view: https://www.drivebc.ca/cameras/681?...9.20589660238912&zoom=13.5&type=camera&id=681
Zero electrical work or drainage work has been done. Another 4-6 weeks to join the bridge deck and you anticipate more delays due to weather.
They might do something stupid where they are sloppy as fuck and open it up to NB only traffic while they continue to do periodic lane closures to redo a ton of work and continue construction through 2026 and 2027.
Troll? The government continues to aim for a 2025 opening which would require some weird road configuration along with multiple temporary fixtures along with a course roadway until they can repave it in the spring/summer. Truth is we are further behind schedule. I'm usually pro-union but this has been a complete gongshow and I hope we can proceed with unionized labour in future public-private partnership involved projects.
You seem to be a bit fixated on the labour aspect of this. Got any insights as to why you're point the finger at site labour rather than other aspects of the construction?
Acciona has been involved in a lot of larger scale infrastructure projects recently, and not all of them have been under the same labour regime.