jollyburger
Active member
And they're only spending $27 million to rehab the current infrastructure for another 30-60 years.
https://vancouver.citynews.ca/2023/12/13/vancouver-trolley-bus-translink/
Back in 2000 they said the trolley infrastructure was worth $184 million
https://www.sfu.ca/person/dearmond/set/Vancouver.etb.replacement.htm
https://vancouver.citynews.ca/2023/12/13/vancouver-trolley-bus-translink/
Back in 2000 they said the trolley infrastructure was worth $184 million
The 309 kilometers of trolley routes are serviced by overhead wire under which 925,000 hours of service are operated annually. The overhead trolley infrastructure has an estimated replacement cost of $184 Million. The existing network of overhead wires has been well maintained with ongoing, routine maintenance and rehabilitation. There is
estimated to be a remaining life of 20 30 years for the overhead infrastructure.
https://www.sfu.ca/person/dearmond/set/Vancouver.etb.replacement.htm