Vancouver Construction Crane Count


^There’s one up directly across St. Davids from the depot for Innova.

We are up to 241, with the usual caveat that there is likely a crane or two on the list already down.

DGCpBXF.jpg
 
Added one crane for Kits Block which went up recently and one for a project in the British Properties in the recently cleared area, haven't been able to ID it yet though.

Also removed one for Henry Hudson (it's a self erecting crane, not a full tower crane, so therefore it's not counted in this list).

241 is nuts, never thought I'd see it that high.
 
Added one crane for Kits Block which went up recently and one for a project in the British Properties in the recently cleared area, haven't been able to ID it yet though.

Also removed one for Henry Hudson (it's a self erecting crane, not a full tower crane, so therefore it's not counted in this list).

241 is nuts, never thought I'd see it that high.

They had a ground breaking for Hawksley and Wildwood with Beedie and BPP back in June:

https://www.instagram.com/p/CwAvZLcM80o/
 
^ It's crazy between Lougheed and Burquitlam Station.

I was in Surrey yesterday, and you can get an awesome view of that area from King George Blvd. It looks like a whole new downtown is going up.
 
they added 2 cranes yesterday at the Baden Park development (Lytton and Seymour) in North van

And the crane came down this week on Hastings @ Boundary (3600 Hastings)
 
Another building at Bridgeport Business Park?

Actually just realised it might be a heavy load lift and not a tower crane.

I guess there's eventually four buildings planned for that development? NW business centre, NE low rise office center, and two hotels fronting Bridgeport?

https://citycouncil.richmond.ca/__shared/assets/3_Application_9520_BeckwithRd_PLN_05071953487.pdf

Actually Hotel 1 got a building permit issued back in February

19 858702 000 00 B7 New Issued 2023/02/21 $40,470,000.00 2888 Jow Street - Hotel 1 IBI Group (Salim Kumar Narayanan) (604)
683-8797 Scott Construction Group (604)874-8228

https://www.richmond.ca/__shared/assets/buildingreportfeb19202366356.pdf

Some Richmond News development permit notice (because some trees on the property died) said it's owned by Chunghwa Hotel Group.

https://citycouncil.richmond.ca/agendafiles/Open_DPP_10-20-2022.pdf

This sales brochure for the Business Centre has one Chunghwa labeled building, a Courtyard Marriott and Residence Inn Marriott (which are on Chunghwa's website)

https://www.republiquegroup.com/wp-content/uploads/2022/04/BC-SALE-BRO.pdf

http://www.chunghwa.ca/hospitality-portfolio/

Chunghwa was originally behind the 888 West Broadway project.
 
Last edited:
900 blk Granville crane removal

Work Description: Please sign both sides of 900 blk Granville St starting from Nelson St going North to Smithe St.

Effective: November 18, 2023: 5:00 am to 8:00 pm

Permission to fully close the 900 blk Granville St for Tower Crane dismantle as per the accepted traffic management plan.

CMBC Special Events – To close or relocate a bus stop, to reroute buses. Inform them of any construction on a bus route and when work impacts trolley busses (i.e. pole pullers or trolley wire shifts): Must complete Temporary Transit Changes Request Form.

Mike Palleschi – report/notify about work near trolley wires. Request trolley wire relocations or de-energization
Email: [email protected]

Transit Communications Centre – To order pole pullers or a pusher truck.
Phone: 778-593-5525

Contact TC Utility Services, the Authorized TOH Power System provider of Qualified Safety Watch
Phone: 604-425-1421


Permit Purpose: Construction

Full/Part Time:

Short/Long Term:

Additional Signage Required: Yes


Start Date: Nov 18, 2023

End Date: Nov 18, 2023

Utility Company: No

https://plposweb.vancouver.ca/Public/Default.aspx?PossePresentation=Guest&PosseObjectId=215397036
 
It's been worked on since the summer. The abatement has been complex, since last summer, and I would imagine the building is almost certainly unsafe in places inside. A building of that height, from that era, might well have a steel frame, and if so they would need the crane to dismantle the building as it's cut up.

The Balmoral has a main steel structure consisting of steel beams and columns with originally solidly built-up 2x4s
infill wood framing. Even though the steel structure does have corrosion, there are no signs of distress in the frame.
Based on the evidence we have to date, we would not classify the main steel structure as an imminent risk of
collapse. We do want to investigate further to determine the extent of corrosion.

https://vancouver.ca/files/cov/2017-218-release2.pdf
 
Thanks Madog! I've been very behind in updating it myself. Been trying to find the time to do it but it just keeps getting busier and busier!
 