AW Leil looks to be setting up another crawler crane, now at Fairview Cove, likely to remove the two aging cranes at the eastern berth.
Nope Confirmed - they are coming down. ( Up-Update - The liebherr is staying. its newer. The old one is original to the terminal opening, and its mate was scrapped a few years ago as it was always broken.)

there is some oversize cargo on the pier that has been using multiple cranes to load onto trucks. might be related to that. I havent heard those cranes were being removed - they still get some use (Unlike the 3 going at halterm, which apparently needed 3 days of de-contamination from all the bird crap in them)