They have been doing quite a bit work in the past two years, but it is not neccessiraly all visible work to you and I.

West corridor:
• In early 2007, the West Corridor project team conducted an internal Value Engineering (VE) exercise to look at ways the project could be more efficient and cost-effective. As a result, FTA requested that an Environmental Assessment (EA) be completed to fully identify and document any impacts of VE.
• By July 2007, final design reached 65 percent.
• In summer 2007, removal of the old rail along the corridor was completed and utility relocation began.
• RTD issued a Draft EA for public comment in fall 2007. A Finding of No Signifi cant Impact decision from the Federal Transit Administration (FTA)
was received in November 2007, with the Final EA issued in late 2007.
• Major construction is scheduled to begin in summer 2008 with the line opening in 2013. (There was an article in the Post regarding the Kipling Street Light Rail bridge as one of the first to get underway)

Union Station:
Work is still being done on the Environmental Impact Statement and is expected to be complete this Fall. The last I heard is that visible work will begin late Fall or ealry next Spring. Lastly, the RFQ has been issued for all of the landscape/streetscape work.