Phase One Construction Update

From the monthly newsletter I receive...

Quote:
The first phase of construction for the Hance Park Revitalization Project is well underway. During this stage of the project, the “Fiesta Bowl Play at Hance Park” play area and surrounding infrastructure, escarpment and landscape will be built. Prior to construction of those features, repairs are being made to Interstate-10 tunnel joints located under the west side of the park. Much of the construction activity to date is related to the joint repairs.
Additionally, excavation and grading are underway, which will modify the park’s elevation for the play area, escarpment and landscape. In the coming weeks, geofoam, which provides a lightweight fill, will be installed. Temporary removal and salvage of trees continues. The work is being done by contractor Haydon Building Corp in coordination with the Arizona Department of Transportation (ADOT).

When the first phase is completed, parkgoers will be able to walk along a 15-foot-wide pathway the length of the escarpment, which will climb gently from east to west. Ultimately, the escarpment will be connected via a pedestrian bridge in a future phase of the project. The bridge will also allow visitors to travel between two separate lawn areas on either side under the escarpment. In the interim condition, access to the west side of the escarpment will be by a set of temporary stairs, which will be removed once the pedestrian bridge and the remainder of the escarpment is constructed. Click on the diagram to the left for an expanded look at park connectivity.
Reply With Quote