9/24/2020

Another ground level concrete pour happened on the northeast corner of the 1st Street site this morning. That leaves one corner left on the northwest side (not visible in the photo except for a small section of rebar).

It does not appear that any work is being done to the sections that have already completed the ground level concrete pours. Maybe this is it for now and it's time to wrap it up like the Mission Street parcel?