Judging from the graphic above the costs could be broken out two different ways:

Phase I - $ 1.249 Billion
Phase II - $ 1.494 Billion
Phase III - $ 1.574 Billion
Phase IV - $ 1.797 Billion

Total - $ 6.114 Billion

... or if you look at the amounts as cummulative:

Phase I - $ 1.249 Billion
Phase II - $ 245 Million
Phase III - $ 80 Million
Phase IV - $ 223 Million

Total - $ 1.797 Billion

Knowing how government spending works... probably scenario one....