So now that Terminal 5 extension is completed, what are the next steps? I recall the plan is to build Satellite 1 and Satellite 2 concourses of the new terminal, before actually closing and demolishing Terminal 2 to give way to the new global terminal.

How about the new indoor parking of Terminal 5?

Is there a timeframe for this?
New parking garage at T5 is under construction and they are doing ground prep work for Satellite 1. They have to remove/move a number of taxiways before S-1 can begin construction.

We are still probably 3-4 years away before T2 gets demo'd.

The city hasn't been very forthcoming with project/timeline updates beyond recently acknowledging that it ain't gonna be done by 2028, thats for sure.