The steel frame building will be a small strip mall, it took them only two days to put up the steel. Foundation forms are going up across from the two buildings with the tower cranes (beside the single building). The road would be paved May 1st at the earliest, that's when Dexter will open their asphalt plants, but even then I don't think there's a real rush for the paving at the moment, lots of other work to be done. The lot just to the east of the school is currently being cleared and the lot to the west of the field is clear and has had many visitors in the last few days. Definitely lots of activity in the area, most of it is concentrated near the highway side working on the underground infrastructure on those streets.