Quote:
Originally Posted by BadHaj View Post
One has to wonder if the whole Pizzarotti debacle at 1 Seaport has anything or nothing to do with the delays here. Meaning, has it inspired them to spend more money and take more time on the more expensive, and more stable foundation than they otherwise would have planned? Interesting...
Doubt it.


Quote:
We chose two years ago to go in the direction of this substantial foundation. We have 470 vertical elements [concrete rods drilled into the ground that create a wall] on the bottom floor—which is 9,000 square feet. It’s something called secant piles. We’re grabbing rock at all these locations.

All the drilling and piling is now completed and now we’re starting on the actual pouring of the foundation. That will go on for four months and it will have taken us two years to do this and a lot more money then we wanted to spend. But the elevators will work perfectly because they will be sitting on solid ground.