April 26th, 2008 Updates
Quote:
Originally Posted by
T-Mac
Down at the site this morning. Met two guys down there who are with the company that is going to spray the side walls this week. They said that they are to start on Monday and it will take them about 5 days to get it finished. The people putting up the backing were running into problems with the walls pushing out and they had to bring in the machine to drive more tie-backs in the north wall to hold it back and keep it from bulging out. Also, you can say good-bye to the 2 trees in front of the site as they should be getting cut down any day now. Here are the photos.
These are the guys that are with the company that is doing the side-walls.
by T-Mac