The on ramps for both bridges have now been graded. Imagine the plan is to use asphalt to pave the path and to landscape the slopes with topsoil and sod and bushes to prevent erosion. Suspect they still plan to paint the bridge steel as well as it is definitely rust coloured now. Not sure on the progress of the path between the bridges on the north side of the river. Hopefully it has been graded and prepped for asphalt paving too. If they pick up the pace there is no reason this shouldn't be open by Sept.