Downtown Adj. - Latest Update Pics, New Multi-Billion $ Salt Lake City Int. Airport

Isaac Riddle Reports - Full Article @ http://www.buildingsaltlake.com/airp...halfway-point/



Isaac Riddle Reports - Construction of the first phase of the new Salt Lake City International Airport has passed the halfway point. The first phase consists of a new consolidated terminal, south concourse, parking garage, gateway welcome center and the recently completed rental car facility...The new airport will have over 70 gates and will be built to LEED Gold standards, making it one of the most energy efficient airports in the country. The new main terminal will be three levels and will be designed to reflect Utah’s geography, with interior and exterior materials intended to resemble the variable terrains that create a sense of place unique to Utah. Included in the main terminal will be an artificial canyon, resembling the canyons of Southern Utah...Besides rising construction costs, the ongoing construction project will require additional workers. According to airport officials, they have employed 700 construction workers so far but will eventually need up to 2,000 workers. Employing that many new workers could prove challenging as the industry is already underemployed...


Earlier Pic of the northeast corner of the west concourse of the south terminal. Image courtesy the Salt Lake City International Airport.


Rendering of the new terminal. Courtesy of the Salt Lake International Airport staff.


Rendering of the new terminal. Courtesy of the Salt Lake International Airport staff.


Rendering of the new terminal. Courtesy of the Salt Lake International Airport staff.


Rendering Overview. Courtesy of the Salt Lake International Airport staff.[/CENTER]


Quote:
Originally Posted by jubguy3 View Post

January 3, 2018 (zoom out!)

  • Began installing windows in South Concourse-West
  • Completed Central Utility Plant masonry
  • Poured concrete on Level 3 of the Parking Garage


South Concourse - West enclosure



West tunnel tie-in



Elevated roadway

Updated Airport Pics By Jubguy3

.
Reply With Quote