View Single Post
  #54  
Old Posted May 3, 2017, 12:11 AM
Keith P.'s Avatar
Keith P. Keith P. is offline
Registered User
 
Join Date: Mar 2006
Posts: 8,019
Washmill was a debacle not because it was in Bayers Lake, but because it was a HRM-managed (ahem) project.

Subsequent to that the lesson was learned to inflate project budgets considerably to provide for a fudge factor for when things go off the rails. This is how we ended up with a $50 million library and a $15 million Oval.
Reply With Quote