Washmill was a debacle not because it was in Bayers Lake, but because it was a HRM-managed (ahem) project.
Subsequent to that the lesson was learned to inflate project budgets considerably to provide for a fudge factor for when things go off the rails. This is how we ended up with a $50 million library and a $15 million Oval.
|