View Single Post
  #10  
Old Posted Oct 14, 2009, 6:27 PM
kaneui kaneui is offline
Registered User
 
Join Date: Sep 2005
Posts: 1,561
A rebuilt Lumberjack Stadium will be part of a new $106M Health and Learning Center at NAU, expected to open in fall, 2011:



Heavy equipment operators do demolition work on Lumberjack Stadium
on the campus of NAU. New work on the stadium and the area around
the stadium will be taking place over the next year.
(photo: Josh Biggs)


Lumberjack Stadium being razed
By JOE FERGUSON
Arizona Daily Sun
October 14, 2009

Crews began tearing down Lumberjack Stadium this week to make room for the new Health and Learning Center. The $106 million project will replace the 40-year-old Fronske Health Center, renovate and expand the 20-year-old Recreation Center and replace the 49-year-old stadium when completed in the fall of 2011. One of the first construction subcontracts issued by the Phoenix-based general contractor, Mortenson Construction, went to Dickens Quality Demolition, also of Phoenix. The contract, estimated to be worth under $1 million, will employ 23 people for roughly the next two months.

Jane Kuhn, an associate vice president, said NAU encourages the selection of local contractors whenever possible. As for the demolition contact, Kuhn said she did not know if there were any local demolition companies. But Todd Sleeper, the owner of Flagstaff-based Eagle Mountain Construction, said his company could have done the work. He said he discussed the demolition contract with Mortenson Construction, but ultimately decided against submitting a formal bid. The strict requirements to meet the green building codes for the Health and Learning Center, he said, made it difficult for him to place a competitive bid. One stipulation, Sleeper said, would have required his crews to separate out the steel from the rubble of the former stadium. Ron Wilson with Mortenson Construction said his company has already given several contracts to local firms, naming Flagstaff- based Ignace Brothers Drywall as one example. Wilson added he has received 43 bids from local subcontractors but has not yet completed its hiring process. He said the next phase will be to pour the concrete foundation and erect the steel frame for the new facility this December.

The construction has already closed off a large parking lot next to Lumberjack Stadium, reducing the number of parking spaces on campus by 230, said Kuhn. Nearby streets won't be immediately affected, said Kuhn, but a different project in several weeks will close off the north end of San Francisco Street on campus. The construction bond will be paid back primarily through students fees. Students are currently paying $290 a year, but the fee will increase to $500 a year by the fall of 2011. The new Health and Learning Center is expected to be open in the fall of 2011.


Tentative project timeline for the Health and Learning Center

Oct. to Dec. 2009: Demolition of Lumberjack Stadium, clean-up

Dec. 2009 to April 2010: Pouring of foundation, steel frame built

April 2010 to Nov. 2010: Bricklaying, installation of drywall and windows

Nov. 2010 to August 2011: Plumbing and electrical work, as well as site work (landscaping, pouring of parking lot)




And another related article:


NAU construction project to create 2,500 jobs, generate $7.3 million in tax revenue
Inside NAU
October 13, 2009

Construction crews began razing Lumberjack Stadium on Tuesday as part of a project that will create about 2,500 jobs and generate more than $7.3 million in city and state tax revenue. Northern Arizona University’s Health and Learning Center, funded in large part through student-approved fees, will add more than $51 million in labor wages to the state’s economy during the 21 months of construction. The 270,000-square-foot facility is expected to open in August 2011. A new and improved Lumberjack Stadium also will be rebuilt as part of the project. The university is planning a groundbreaking ceremony for the project on Oct. 22, when alumni return to campus for Homecoming activities that week. “Construction is one of those areas that can help boost a sagging economy,” said NAU President John Haeger, who is an expert on economic change in America. “I’ve said before that you can’t just cut your way out of a recession. By investing in jobs that will bring positive change to campus, we are helping our students while also benefitting our local and Arizona workforce.”

The Health and Learning Center will replace the 40-year-old Fronske Health Center, renovate and expand the 20-year-old Recreation Center and replace the 49-year-old stadium. It will include two floors of much-needed classrooms and an integrated service center providing physical health, mental health, recreation, intercollegiate athletic facilities, a café and social gathering space. The $106 million project also encompasses the recently opened recreation fields, volleyball courts and facilities on south campus. As with the fields project, the Health and Learning Center will be built to the Leadership in Energy and Environmental Design standards of the U.S. Green Building Council.

“The increase in construction-related jobs is particularly welcome in this economy since the construction sector typically pays among the highest average wages when compared with jobs in other industries,” said Ron Gunderson, NAU professor of economics. “The project will not only increase jobs in the private sector, but the expenditures for goods and materials in the local area also generate increased sales tax revenues for the city of Flagstaff. Sales tax receipts in most of the local sectors have been significantly reduced over the past year due to the economic slowdown, so the addition of an expected $1.4 million in new city sales tax revenues will be a welcome addition at this time,” Gunderson said.

The university has worked closely with the selected contractor, Mortenson Construction, to encourage participation of area subcontractors, according to Jane Kuhn, associate vice president for Enrollment Management and Student Affairs. “Mortenson ran a series of ads in the Arizona Daily Sun during the month of May and sponsored a meeting, with assistance from the Northern Arizona Builders Association, inviting local subcontractors to participate in the project,” Kuhn said. “They also reached out to the local subcontractor community through a calling campaign that began in early May. While the contractor is working diligently to solicit local participation, state procurement law requires acceptance of qualified low bids.”

Mortenson already has received 43 bids from local subcontractors but has not yet completed its hiring process. Five other projects slated on campus, which will be funded differently, also will provide an economic stimulus for the city and state. The projects are part of the legislative Stimulus Plan for Economic and Educational Development, or SPEED, which would be funded primarily through future Arizona Lottery revenue deposits. Budget challenges have delayed the projects, which have been approved by the Arizona Board of Regents and received favorable review by the Legislature’s Joint Committee on Capital Review. They include critical upgrades of the Liberal Arts building, the former Inn at NAU and the North Union as well as improvements to the north campus plant and utility delivery. The Skydome project will address issues related to access for people with disabilities and fire- and life-safety concerns. It is estimated that the SPEED projects will create 1,500 jobs with a labor income of $31.3 million. The combined city and state tax revenue is estimated at $4.6 million.


Lumberjack Stadium to get total makeover


This rendering of the new Lumberjack Stadium shows seating for 1,000 sports fans.
The stadium will be an integral part of the new Health and Learning Center. Both are
slated to open in August 2011.
(render: NAU)


Lumberjack Stadium is being torn down, but like a phoenix, it will rise again. Originally built in 1961, it is going away to make way for a newer Lumberjack Stadium that will seat 1,000 sports fans comfortably and serve as an integral part of the new Health and Learning Center. The new stadium will have more room for concessions and include a new press box and space for athletic teams and public facilities. The rebuilt stadium will house facilities for women’s soccer and golf and men’s and women’s tennis, including locker rooms, training facilities, meeting rooms and offices. The stadium upgrade will include replacing the track turf, and lighting around the field will be Dark Skies compliant. Original Lumberjack Stadium dedication plaques will be put on display in the athletics area lobby of the new facility.

Last edited by kaneui; Oct 14, 2009 at 7:10 PM.
Reply With Quote