Quote:
Originally Posted by Blah_Amazing
|
I didn't dig deep but it seems Hines is under the impression they would have until July 26, 2023 as they believe the approval started once the 10-day appeal period following the approval was over. The city's approval seems to make clear that they are using the July 15, 2023 date, but they also say "Planning staff is recommending that the
requested one-year time extension for this project be granted" so I am a bit unclear - but I guess we will find out if they file anything this week
Interesting that Hines cites 80 days of delay due to opposing parties filing an appeal against the design review approval. "Due to the ongoing legal action, the Project Owner was unable to proceed with the necessary design processes from July 26th, 2021, until October 14th, 2021."