January 22, 2021 – For the next two weeks:
Level 19 floor slab of the South Tower will be formed
Level 11 floor slab on the East side of the North Tower will be placed
Level 11 floor slab on the West side of the North Tower will be formed
Façade restoration on the West Georgia Street elevation will continue
Block wall installation will continue on floors up to Level 11
Drywall partitions and bulkheads will continue on floors up to Level 15
Fireproofing of the existing steel will continue up to Level 7
Concrete demolition will continue throughout building
Elevator installation will continue in the Podium levels
Exterior wall framing and glass installation will continue along Dunsmuir Street
Curtain wall glass installation will be ongoing on Level 10 of the South Tower
Civil services to the building will along Homer Street for the next four weeks
The Hamilton Street sidewalk adjacent to the building will be closed for the duration of the project
The Hamilton Street southbound curb lane will be closed daily from 7:00 am to 8:00 pm (Monday – Saturday)
The Homer Street curb lane will be closed for the duration of the project
Noise exemption permits will be applied for all weekends and concrete pour days until further notice
|
|