Quote:
Originally Posted by JMKeynes
Demo will be done in 3 months? That would be great!
|
Quote:
Originally Posted by Shwayze1994
I didn’t think this one would go up so fast. But just to think in a year this will be well above the ground.
|
Demo is already behind, there's about a quarter left. The building has been under construction for over a year. They have to turn over the rebuilt Eastside Access - which runs underneath the site - to the MTA by the end of June. That work has been ongoing, just not visible for obvious reasons. But you can follow what work is going on at the site by reading the DOB filings.
Anyway, they are already behind (as is everything else), but you can see how the construction phasing will work by looking at the scheduling graphics provided.
They'll begin above ground construction on the western side (before demo is complete), and work eastward in sequence.