⚠️ CONSTRUCTION UPDATE ⚠️

The entire new roadway of Convention Center Boulevard, from Poydras to Henderson Streets has reopened! With the completion of the improved city side of Convention Center Boulevard, our crews are continuing work constructing the 7.5-acre public park that runs the length of the building.

The New Orleans Ernest N. Morial Convention Center Linear Park project is currently 80% complete with an estimated completion date of October 2020. Read more below.







Pile Driving is underway at TMG's latest project with the City of New Orleans. The Criminal Evidence Processing Complex will be a 58,876 sq ft, five story building when completed.
#whatwillyoubuildtoday #progress