Originally Posted by 427MM View Post
Fun updates! Keep 'em comin. Ran into the architect on Thursday and he shared that the portion in the street took around four months longer than expected. Both Austin Water and Austin Energy decided to change their design plans once the word had begun. Really wish we'd demand more from the City of Austin when it comes to delivering consistent, predictable service free of meddling and unknowns. One can dream.

He also shared that for the next few months the work will be difficult to see as they shore up the walls of the State Theater. But fear not, it is moving ahead and is underway.