Nov 19, 2019 article:
Quote:
Members of New Westminster’s arts community are giving a standing ovation to a new housing project that’s getting underway.
Work is getting underway this month on a project at 831 Carnarvon St., which includes 204 market condominiums in the 32-storey Ovation building and 66 non-market rental units in the eight-storey PAL New Westminster building. The project is aiming to be complete in the summer of 2022.
PAL New Westminster will include 25 studios and 41 one-bedroom units for those from arts-oriented professions with low to moderate incomes, with priority going to seniors and people with disabilities.
...
|
The 8 storey building will likely be completed by summer 2022 but it's a safe bet that the 32 storey Ovation will more likely be completed a year later. Sure the garages were knocked down over a year ago but they didn't start digging until now, which only gives them 2 and a half years to have it finished in summer 2022 - I really don't see that happening at this location.