View Single Post
  #145  
Old Posted Sep 27, 2017, 7:00 PM
whatnext whatnext is online now
Registered User
 
Join Date: Feb 2009
Location: Vancouver
Posts: 27,373
I wonder how opinion on Site C will change now that it's been exposed to have been overbudget from Day One.

B.C. Hydro was nine per cent over budget and already dipping into contingency funds from day one on the main construction contract at Site C, according to the uncensored version of a report to the B.C. Utilities Commission.

The troubles continue to the present day, with the $1.8 billion main civil works contract having run through three quarters of its contingency budget with only one quarter of the work being done...


http://vancouversun.com/opinion/columnists/vaughn-palmer-b-c-hydros-site-c-promises-ring-hollow
Reply With Quote