Construction start next week
Just received from a source:
Please note that Management was just informed today that McHugh Construction will be mobilizing next week to commence construction of 1200 S. Indiana. They will first clear the site, as well as erect fencing around the perimeter. They will also establish the private alley connection through to Michigan Avenue. Drilling of deep foundations is anticipated to begin by the beginning of January 2017 and will take approximately 2 months. Finally, excavation and construction of the rest of the foundation system and related underground work will carry on through the end of May 2017.
|