View Single Post
  #1652  
Old Posted Dec 3, 2016, 1:00 AM
Spr0ckets Spr0ckets is offline
Registered User
 
Join Date: Oct 2015
Posts: 1,964
Quote:
Originally Posted by GilmoreStation View Post
How many floors do you think they can build for the entire year of 2017?
Typical towers with average floorplate sizes (not too large or too small) usually take about a week to a week and half or so for each floor plate/slab (structural only).

With 52 weeks in a year you're probably looking at anywhere between 40-50-ish floors for most of the year assuming they start the year having cleared the podium entirely and also assuming no unusual conditions or delays or any weeks taken off from construction (like....construction holiday in the summer, for instance).


Rough estimates and speculative, of course.
Reply With Quote