Quote:
Originally Posted by dharper View Post
I forgot to mention in this thread(I did in the closed Port Mann Hwy1 thread), the surveyors were out every day, for several months starting in December last year. Then there was nothing for the summer months. And now they have been back for several days now.
Again, I don't know this project, but your description makes sense. They were out first to gather all relevant information required for the design, then there was design time (and a lot of other tasks), and recently they could be out to get information specific to the design that was developed: checking locations and their local geology, checking bearing capacities, checking extents and volumes of material that may need to be removed, and so on.