Based on the 150 stacking plan, the first straight up steel starts on the 8th floor. If that is the case, the webcam indicates that they are currently:
- installing the glass panels on the 18th floor
- erecting steel on the 34th floor
- pouring the core on the 39th floor
If they don't count the 13th floor, these counts could be off by one. Here is hoping they are still going to 54 floors.