View Single Post
  #10121  
Old Posted Jul 1, 2015, 12:36 AM
typo86's Avatar
typo86 typo86 is offline
Registered User
 
Join Date: May 2010
Posts: 202
New Airport Terminal...

$650 million Armstrong Airport project on schedule as it heads into construction phase



The design of New Orleans' $650 million airport terminal is nearly complete, clearing the city's construction manager to begin doling out lucrative building contracts, officials said Tuesday (June 30).

The final construction documents for the Louis Armstrong International Airport North Terminal should now be complete, triggering a 30-day period during which the construction manager will have to select its contractors and finalize the maximum price it will charge the New Orleans Aviation Board, said Chris Spann, who is managing the project for the body that oversees the airport...

http://www.nola.com/politics/index.s...incart_gallery
Reply With Quote