Hamilton’s stadium is “substantially complete”
Hamilton Spectator
By Matthew Van Dongen
http://www.thespec.com/news-story/5609721-hamilton-s-stadium-is-substantially-complete-/
Hamilton can finally take over its $145 million stadium next week – and now the race is on to get it event-ready.
An independent certifier for Infrastructure Ontario alerted the city Friday evening that the long-delayed construction project has achieved "substantial completion."
That means the city finally gets the keys – 10 months later than expected – and beleaguered contractor Ontario Sports Solutions gets $89 million of withheld payments.