View Single Post
  #34  
Old Posted Nov 4, 2014, 1:13 AM
Keith P.'s Avatar
Keith P. Keith P. is offline
Registered User
 
Join Date: Mar 2006
Posts: 8,816
Quote:
Originally Posted by JET View Post
HRM and the Shubenacadie Canal Commission jointly undertook two major studies for the
Canal Greenway between Sullivan’s Pond and Halifax Harbour. Each of these studies, prepared in 2003 and 2006 by professional engineers, landscape architects and planners, concluded that it was feasible to daylight a large portion of the existing stormwater pipe, extending from the intersection of Portland Street and Prince Albert Road across "Irishtown Road and up onto a portion of the Starr Manufacturing site. This would allow a substantial surface stream. A plan prepared for the SRA in 2012 by a fisheries biologist demonstrated how a surface stream could be created to provide fish passage, while a revitalized underground pipe would continue to carry most of the stormwater below grade. Neither option interferes with the preservation or interpretation of historic features on the site."
https://www.ecologyaction.ca/files/image...er/Briefing%20Note_Sawmill%20River_0.pdf
I don't think anyone is suggesting that we have daylighting and no stormwater backup. We can have our cake and eat it too!

All it takes is our money!

If the EAC is for it, I'm against it.
Reply With Quote