The Seaholm website has an updated timeline for the progress that's planned:
April, 2013: Excavation for garage begins
December, 2013: Power plant interior demo work complete
January, 2014: Tower foundation complete
February, 2014: Front lawn complete
March, 2014: Power plant dry-in complete
April, 2014: Low rise exterior work
June, 2014: Power plant ready for tenant finish-out, low rise ready for tenant finish-out
July, 2014: Underground garage and streets work complete
September, 2014: Tower ground level ready for tenant finish-out
May, 2015: Tower exterior complete
June, 2015: Tower last unit ready for lease
|