Okay guys, so 2012 is over with and it was a pretty good year for Austin. We saw development finally pick up again to pre-2008 recession levels. Many projects were announced and begun. It's looking like 2013 will be even bigger. I figured I'd make a list of downtown projects for the new year. Please correct me if you have more up-to-date information or if I forgot anything. (BTW, we need to update the list on the front page, too.)
Projects that will be starting in 2013:
- Shoal Creek Walk - early 2013
- 6th & Lamar (former KVET studios) - early 2013
- Capital Studios (11th & Trinity) - early 2013
- 3rd and Colorado - early 2013
- GreenWater - early 2013
- Fairmont Hotel - March 2013
- New Central Library - Summer 2013
- IBC Bank Plaza - 2013
- Seaholm - 2013
- 7Rio - 2013
- StreetLights at Barton Springs - 2013
- Broadstone at the Lake - 2013
- 300 East 5th Street Hotel
- Hotel Van Zandt - 2013
- Hotel ZaZa & Apartments -2013
- UT System Headquarters -2013
- Rainey Center - late 2013
Projects that will be completed in 2013:
- The Whitley
- Gables Park Plaza II
- Eleven Austin
- Hyatt Place
- RiverView Apartments
- Calloway House
- 2400 Nueces
- West Campus Tower
Projects that will continue construction in 2013:
- JW Marriott Hotel
- 3eleven Bowie
- SkyHouse Austin
- East Avenue apartments
|
If you are counting 78704 in the list: The Tree and Gibson Flats will both be completed in 2013. The new development at South Lamar Plaza will also continue construction in 2013.