View Single Post
  #1006  
Old Posted Aug 4, 2010, 2:17 PM
Dado's Avatar
Dado Dado is offline
National Capital Region
 
Join Date: Jul 2007
Location: Ottawa, Canada
Posts: 2,521
Quote:
Originally Posted by Sir.Humphrey.Appleby View Post
They have to double track and triple track some rather tight segments with hills/valley walls (not exactly sure if you could say cliffs) bounded by the river on the other side, mostly running through a Provincial Park. In all, not the easiest proposition, hence the cost.
It's still not going to cost half a billion for upgrades to less than 40 km of track. Where did you get that figure from?

The final report of the CRP from last December - which had representatives from Canadian Pacific - has the following to say about capital costs (p. x of the Executive Summary):

The estimated total capital costs (in 2008 dollars) for providing three peak commuter rail branches, one to Cochrane, one to Airdrie and one to High River/Okotoks, is $1.2 to 1.3 billion, or about $285 to $330 million per corridor, and approximately $250 million for downtown trackage and station requirements, contingencies and spare vehicles.
__________________
Ottawa's quasi-official motto: "It can't be done"
Ottawa's quasi-official ethos: "We have a process to follow"