Project Status Report
As of May 7, 2008
Project and Budget Approved
Engineering building - February 2009 - ($38 million) Tower crane has been removed. Mechanical and electrical rough ins 15% complete. Curtain Wall installation to commence in May 2008.
McMaster front entrance - Summer 2008 - ($5 million) Design work complete. First stage of landscaping to be implemented with construction of the new Engineering building in 2009.
Burke Science Building - Spring 2008 - ($41 million)
Ronald V Joyce Stadium - February 2008 - ($33,500,000) Garage is complete and being occupied. Stadium participant section work 95% complete. Stadium 96% seating completed. Turf subbase work completed. Turf installation has commenced.
MDCL 2nd floor fitout - Summer 2009 - ($26 million) Working drawings complete. RFP for construction manager has closed. Developing detailed cost estimate and schedule with Construction Manager.
Thode Library Learning Commons - ($850,000) Phase 1 (ground floor renovation) is in design stage amd work to commence this May.
Project not Approved and Budget Pending
Main Entrace Building Complex for the Faclties for Engineering Science, & health Sciences (Phase 2)
Burlington campus - Fall 2009 - ($35 million) Business plan and functional plan currently being developed. Alternate locations from the original downtown location are being considered.
Under consideration
Liberal Arts Building - Functional programme development to be completed in Spring 2008
For future consideration
Above Ground Parking Structure - On hold pending a campus wide parking review
Sports Arena - Would be looked at offsite
Tennis Courts
|