Project Status Report
As of January 8, 2008
Project and Budget Approved
Engineering building - February 2009 - ($38 million)
McMaster front entrance - Summer 2008 - ($5 million) Design work complete. First stage of landscaping to be implemented with construction of the new Engineering building in 2008.
Burke Science Building - Spring 2008 - ($41 million)
Ronald V Joyce Stadium - February 2008 - ($33,500,000) Tendering 99% complete. 99% of garage related concrete complete. 95% mechanical/electrical site work complete. Structural steel complete. Precast concrete stands complete. Stadium participant work 85% complete. Work on media box has commenced.
Project not Approved and Budget Pending
MDCL 2nd floor fitout - Summer 2009 - ($26 million) Architect retained to provide schematic design. Final approval pending.
Burlington campus - Fall 2009 - ($35 million) Business plan and functional plan currently being developed.
Project not Approved, Under consideration
Liberal Arts Building - a space audit of existing space within the Faculties of Social Sciences and Humanities has been completed. Functional programme development to be completed in Spring 2008
Thode Library Learning Commons - Preliminary concepts have been produced for an open house in late November to receive feedback on potential scope.
Above Ground Parking Structure - On hold pending a campus wide parking review
Sports Arena - offsite location
Tennis Courts
|