Site recaps from 4/3 & 4/6 via
hindesky on HAIF
4/3
Quote:
All the fencing has been removed and the entrances replaced with barricades. Those barricades all have the same sign on them saying that people will no longer be able to park here after Monday 4/6/2026 or they will be towed. Only the eastern Argonne St. entrance has 1 barricade so people can still get in to park for now.
4/6
Quote:
Went by this project once again. I saw 2 Baker Concrete workers thinking they would be doing the concrete for the project but they said they are only doing the concrete of the former bank foundation and all the parking lot demolition and not doing the building itself. They were surveying the property to estimate how much concrete they would be removing. They didn't know who the concrete contractor would be.
Last time Andres built a high rise here in Houston they used Keystone Concrete to build the Parkside Residences next to Discovery Green so that may be who they use. Saw a couple of landscapers cleaning the property of leaves and weed eating what little grass there was and 2 other people who might be from Andres or Southern Land Communities. They talked with a tow truck driver, I'm assuming who they contracted to tow vehicles parking on the property and driveways.
The orange barriers had been filled full of water.
__________________
Houston :
New Big/Tall Stuff
-
New Not so Big/Tall Stuff
-
Suburban Stuff
-
Airport(s) Stuff
-
Ports & Industry Stuff
-
Parks & Civic Space Stuff
-
Sports Stuff
-
Spaceport/Space Center Stuff
Wattleigh
View Public Profile
Find all posts by Wattleigh