Posted May 31, 2025, 7:27 PM
|
|
Registered User
|
|
Join Date: Jun 2016
Location: London
Posts: 9,193
|
|
Wrapping up the final residential 29th floor and have started forming for the mechanical penthouse. Have also now removed the concrete pump arm. Window glass is now installed up to the 24th floor level and have started installing the balcony railing glass on the lowest floors. Still no signs of any masonry work on the faux Talbot streetscape lobby.
|