900 King St W Kitchener
@CuilTard 07-22-2024
@CuilTard 07-27-2024
Station Park Kitchener
@CP42 08-08-2024
15/36
Fischer-Hallman & Bleams development
@ZEBuilder 08-08-2024
Quote:
|
The soldier piles for the shoring is also mostly complete, they only have a few more piles left to go. They were also working on the lagging between the piles in a few places today. It looks as if the shoring is only going along the plaza's access road and the BMO parking lot/future commercial building, they have also installed some shoring along Fischer Hallman where the guy wires for the hydro poles are but the way the excavation is makes it impossible for any other shoring to be installed along Fischer Hallman or Bleams.
|