137-141 George St | 70m | 22f | U/C
The subject property owned by Claridge Homes has previously been approved for Site Plan Control in 2013 (#D07-12-12-0199), which includes other adjacent lands (110 York, 321-325 Dalhousie), for the conversion of an existing office building to a hotel (completed) and the development of a 22-storey mixed-use (commercial/residential) building on the subject site (137-141 George St).
The project also includes the development of an underground parking garage that will serve the hotel and residential components. Architect: NEUF Architect(e)s Development application (long gone): http://app01.ottawa.ca/postingplans/appDetails.jsf?lang=en&appId=__8E3BLV Siteplan: https://i.imgur.com/9FtwgzG.png Renderings: https://i.imgur.com/kTm2DJ8.png https://i.imgur.com/254xpnL.png https://i.imgur.com/QU1ROVo.png https://i.imgur.com/Hv0pHIt.png https://i.imgur.com/GX1NHZd.png https://i.imgur.com/J2apkRO.png |
137-141 George St | ?m | 22f | U/C
Pile Driving underway for Phase 2
https://live.staticflickr.com/65535/53863655286_4039bfc8a8_b.jpg https://live.staticflickr.com/65535/53864068415_d0f0d0a10f_b.jpg |
So they're building the hotel addition and the 23 floor tower at the same time?
|
Quote:
|
Quote:
|
Quote:
What has Mark Sutcliffe done in his administration so far? I don't recall the last time I heard anything out of city hall. |
Quote:
He picked fights with NCC over closing one road. Even if you agree with him it seems petty and ineffective. He opened a station as promised in the Rideau Centre not the actual market but they seem to be starting to patrol a bit. Can't think of anything else. |
Quote:
This guy is in way over his head. The problem is that all you need to do is proclaim yourself as a “man of the taxpayer” and vow to fight against all the leftie-looney bike lanes, and people in this city will eat it right up. |
Sutcliffe introduced a bunch of transit cuts (War on Transit!). The guy who was supposed to be the tourism and business Mayor has severely cut the City's contribution to the Tulip Festival, amongst others. Cuts to secure bike parking budget. He's ready to write a blank cheque for Lansdowne though.
Back on topic, image from Saturday: https://cdn.skyrisecities.com/forum/attachments/1722352802504-png.584522/ Someone on Skyrise posted pics that show the excavation so far. https://ottawa.skyrisecities.com/forum/t...59-37-16s-18s-claridge-homes-neuf.24117/ |
|
Quote:
|
Quote:
https://www.lowertown-basseville.ca/uplo...n-shot-2023-11-17-at-5-35-48-pm_orig.png https://www.lowertown-basseville.ca/ |
Would be surprised they would do the underground parking and dig for both the Andaz Extension and Andaz Apartments/Condos which we haven't heard of in years...
Also is it just me or does the dig seem to take the entire space between Andaz and the new Moxy? I thought there was a parcel in between that originally had a Hampton Inn proposal of some kind, did Andaz acquire that land? |
Quote:
|
Wonder if they're digging the entire parking garage, but might hold off on building the towers. If they did buy the Hampton Inn site, they would need to go back to the drawing board and re-jig the entire site. I don't want another Rideau clump to add to the Eastern Block.
|
From hoggytime on Skyrise, Andaz, Hampton Inn and the condo approved a decade ago all being excavated at once.
Hoping they are digging in preparation for a new proposal encompassing the entire lot. This particular parking garage was never approved. https://cdn.skyrisecities.com/forum/attachments/dji_0057-hdr-jpg.611054/ https://ottawa.skyrisecities.com/forum/t...16s-18s-claridge-homes-neuf.24117/page-2 |
So did the developer purchase the site? I know the Hampton Inn site was for sale a few years ago, wonder if they acquired it.
Cramming the Andaz, Andaz extension and a Hampton Inn on that lot was always going to look awkward and packed. |
Quote:
I agree, the Andazx2 and Hampton Inn would create another Rideau wall. I would prefer a three story podium on the whole site with point towers on top over the proposals we have now. |
Combined Parking Proposal (Feb 2025)
The subject property is located in the ByWard Market area and is an assembly of six lots. Two lots have frontage on York Street (110 and 116 York St, currently vacant), two lots have frontage on George Street (137 and 141 George St, currently under construction for a high-rise residential building), and two lots have frontage on Dalhousie Street (321, 325 Dalhousie St, currently occupied by the Andaz hotel). The surrounding area includes low-rise commercial uses, high-rise, and mixed-use buildings. A Site Plan approval (File No. D07-12-12-0199) was granted in 2014 for the Andaz hotel located at 321 and 325 Dalhousie Street and for a 22-storey residential building located at 137 and 141 George Street. The Andaz hotel has been built and the Owner is currently constructing the residential building at 137 and 141 George Street. The purpose of this Site Plan Control Revision application is to revise plans related to the underground parking garage for the 137 and 141 George Street development to permit the extension of the underground parking garage to also be located on 110 and 116 York Street. The intent is for this underground parking garage to be shared by all the uses located on these lands. The approval of this Site Plan Control Revision application would allow the shared underground parking garage to be built in advance of any future above-grade work on 110 and 116 York Street, for constructability purposes. Development application: https://devapps.ottawa.ca/en/applications/D07-12-24-0116/details Plan: https://i.imgur.com/Nd62YKj.png |
Quote:
|