invisibleairwaves Dec 13, 2019 7:46 PM

[Coquitlam] Burquitlam Park | 50fl, 30fl, YMCA | U/C
 
Quote:

https://images.glaciermedia.ca/polop..._804/image.jpg

A YMCA community centre is part of a package of amenities agreed to in a three-way partnership between the city, the YMCA of Greater Vancouver and developer Concert Properties.
Photograph By CONCERT PROPERTIES

"After years of planning this innovative and complex project, we're thrilled to soon be seeing shovels in the ground," Mayor Richard Stewart said Monday after council unanimously approved the necessary zoning amendments and a budget for the project. 'This partnership provides substantial benefits to the city, bringing significant new amenities and much greater value than we could have achieved on our own."

The deal struck between the three partners was five years in the making.

As part of the agreement, Coquitlam will provide 1.3 acres of Burquitlam Park to Concert Properties, which will use the land for the construction of a mixed-use development and the new YMCA facility. In exchange, Concert will provide the city with 2.55 acres of land at Whitgift Gardens and $700,000 for the expansion of Cottonwood Park.

The city has budgeted $42 million for its share of the community centre, $5.5 million for the park-and-ride and $4.7 million for the community police station. YMCA will contribute $38 million for the rec facility for a 50% ownership share and will cover ongoing operations and asset replacement over the life of the building. Concert will oversee all of the construction.

"We have shown through partnerships with non profits, community providers, developers, that we can do so much… and those give us greater opportunities than when we just go it alone," said deputy city manager Raul Allueva, who was the general manager of parks and recreation when negotiations began. "We can do incredible things across those boundaries that provide value."

The construction timelines will be tight. Staff said that site prep work will begin immediately, with an official groundbreaking likely taking place early in the new year.

The Cottonwood Park expansion should be completed in spring 2021 while the YMCA rec centre, community police station and park-and-ride are expected to be completed by fall 2022. Construction of the rental housing component of the mixed-use development will be completed in 2023.

"We are going to get on the site very quickly," Allueva said. "The community needs this community centre and we need to get going on this."

Community amenities are not the only benefit the city receives through the joint partnership. More than 1,000 units of purpose-built rental, including 100 units of non-market rental housing, are planned for the site, which a staff report said is a three-to-one replacement.

Stephen Butz, president and CEO of the YMCA of Greater Vancouver, told The Tri-City News he was "astounded and thrilled" to see Coquitlam council unanimously pass the necessary zoning amendments and budget for the project Monday night. He added that having a headquarters in area will improve the service offerings the organization provides in the Tri-Cities.

"So much goes on here relative to the scope of services that offer," Butz said. "This will be the hub."
https://www.tricitynews.com/news/ren...ect-1.24032253

PDF with full project details including the Whitgift site

From Concert's press release:

Quote:

The planned construction schedule is:

December 2019: Burquitlam Park site fencing and site preparation, including clearing of park amenities and vegetation
January/February 2020: Start of excavation
Spring 2021: Cottonwood Park expansion completed
Fall of 2022: Construction of YMCA, Community Police Station and Park-and-Ride completed
2023: Construction of rental housing and portion of Burquitlam Park completed

The southern portion of the new Burquitlam Park will open to the public when the YMCA is completed. The park will be completed with the development of the strata tower, which will depend on market conditions.
Sounds like the 50-storey strata tower might be a little while down the road- I'm not actually sure whether the development permit was approved for the towers on Monday night, or just for the YMCA, as the rezoning for the entire site was part of the same motion.

Tetsuo Dec 14, 2019 12:23 AM

Between this YMCA, Chimo/Poirier, and Burnaby's plans for Cameron Rec Centre, the Burquitlam area is going to be quite well served by public amenities !!!
Edit/Delete Message

SpongeG May 16, 2020 4:01 AM

May 15

https://live.staticflickr.com/65535/...7be5f5a9_b.jpg2020-05-15_08-29-36 by snub_you, on Flickr

The house in the pic seemed to not want to sell for months, all its neighbours sold and it seemed to resist, but now its up for sale and been quite a few months on the market. The houses next to it were demolished and a 4 or 6 storey proposal will replace them.

https://live.staticflickr.com/65535/...364631ac_b.jpg2020-05-15_08-29-44 by snub_you, on Flickr

This is only part of the site, phase 1, pretty big site.
https://live.staticflickr.com/65535/...3e46b9a6_b.jpg2020-05-15_08-30-01 by snub_you, on Flickr

https://live.staticflickr.com/65535/...03b568cb_b.jpg2020-05-15_08-30-09 by snub_you, on Flickr

https://live.staticflickr.com/65535/...cce1e78e_b.jpg2020-05-15_08-30-17 by snub_you, on Flickr

https://live.staticflickr.com/65535/...2b441850_b.jpg2020-05-15_08-30-26 by snub_you, on Flickr

Klazu May 16, 2020 4:27 PM

Has there been any rendering of the two towers?

SpongeG Aug 1, 2020 1:59 AM

July 31

they have made a more defined road with new paving not really able to see it in the pic but when in the area you can get a better sense.
https://live.staticflickr.com/65535/...85f99cdd_b.jpg2020-07-31_06-19-50 by snub_you, on Flickr

https://live.staticflickr.com/65535/...2e5deaba_b.jpg2020-07-31_06-20-00 by snub_you, on Flickr

the 33 storey tower and YMCA will be constructed first, hopefully the 51 storey tower isn't too long off.
https://live.staticflickr.com/65535/...8e09113b_b.jpg2020-07-31_06-21-10 by snub_you, on Flickr

https://live.staticflickr.com/65535/...e5705f49_b.jpg2020-07-31_06-21-22 by snub_you, on Flickr

https://live.staticflickr.com/65535/...c0b78c2f_b.jpg2020-07-31_06-21-33 by snub_you, on Flickr

https://live.staticflickr.com/65535/...cac5462b_b.jpg2020-07-31_06-21-48 by snub_you, on Flickr

the fence is at a straight drop down into the pit, was nervous taking pics lol in case i dropped the phone
https://live.staticflickr.com/65535/...f9491d54_b.jpg2020-07-31_06-22-03 by snub_you, on Flickr

https://live.staticflickr.com/65535/...53f7c640_b.jpg2020-07-31_06-22-12 by snub_you, on Flickr

https://live.staticflickr.com/65535/...bbc96b42_b.jpg2020-07-31_06-22-22 by snub_you, on Flickr

SpongeG Oct 21, 2020 12:53 AM

Oct 20

https://live.staticflickr.com/65535/...a640d4c7_b.jpg2020-10-20_05-28-01 by snub_you, on Flickr

https://live.staticflickr.com/65535/...f00492f3_b.jpg2020-10-20_05-28-08 by snub_you, on Flickr

https://live.staticflickr.com/65535/...bd75f939_b.jpg2020-10-20_05-28-13 by snub_you, on Flickr

the left is the 33 storey tower - the right must be the YMCA
https://live.staticflickr.com/65535/...7b03c515_b.jpg2020-10-20_05-28-19 by snub_you, on Flickr

https://live.staticflickr.com/65535/...541e81cd_b.jpg2020-10-20_05-28-24 by snub_you, on Flickr

this will be underground/underneath of the park
https://live.staticflickr.com/65535/...3863e5d5_b.jpg2020-10-20_05-28-30 by snub_you, on Flickr

https://live.staticflickr.com/65535/...dab1dbec_b.jpg2020-10-20_05-28-34 by snub_you, on Flickr

https://live.staticflickr.com/65535/...c3711c9a_b.jpg2020-10-20_05-28-39 by snub_you, on Flickr

https://live.staticflickr.com/65535/...7b70bc9f_b.jpg2020-10-20_05-28-45 by snub_you, on Flickr

https://live.staticflickr.com/65535/...f6bc81bb_b.jpg2020-10-20_05-28-52 by snub_you, on Flickr

https://live.staticflickr.com/65535/...dd3f5430_b.jpg2020-10-20_05-28-57 by snub_you, on Flickr

LeftCoaster Oct 21, 2020 1:35 AM

Wow they are a lot further along than I expected. By that tower crane diagram it looks like they arent currently constructing the strata tower though, hopefully they push that one to sales quickly if they havent already.

vanman Oct 21, 2020 1:46 AM

Thread title needs to be changed to u/c.

SpongeG Oct 21, 2020 2:49 AM

Quote:

Originally Posted by LeftCoaster (Post 9079928)
Wow they are a lot further along than I expected. By that tower crane diagram it looks like they arent currently constructing the strata tower though, hopefully they push that one to sales quickly if they havent already.

yeah it's on hold for now, but there is a sign explaining the project on the fence that says the YMCA and rental tower will be complete 2022-23 and the entire project complete by 2024. I assume that is the strata tower part.

jollyburger Oct 21, 2020 3:05 AM

Quote:

Originally Posted by SpongeG (Post 9079997)
yeah it's on hold for now, but there is a sign explaining the project on the fence that says the YMCA and rental tower will be complete 2022-23 and the entire project complete by 2024. I assume that is the strata tower part.

YMCA and the parkade is 2022 and rental is 2023.

Lexus Nov 11, 2020 4:22 AM

2020 November 10

https://live.staticflickr.com/65535/...a90c7281_h.jpgUntitled by Lexus, on Flickr

Lexus Nov 30, 2020 2:39 AM

2020 November 29

https://live.staticflickr.com/65535/...088468eb_h.jpgUntitled by Lexus, on Flickr

https://live.staticflickr.com/65535/...854da3b6_h.jpgUntitled by Lexus, on Flickr

SpongeG Jan 16, 2021 10:20 PM

January 15

https://live.staticflickr.com/65535/...5776208f_b.jpg2021-01-15_08-26-05 by snub_you, on Flickr

https://live.staticflickr.com/65535/...c73bc317_b.jpg2021-01-15_08-26-34 by snub_you, on Flickr

https://live.staticflickr.com/65535/...fbee8700_b.jpg2021-01-15_08-27-08 by snub_you, on Flickr

https://live.staticflickr.com/65535/...a8295f90_b.jpg2021-01-15_08-27-36 by snub_you, on Flickr

https://live.staticflickr.com/65535/...5d11fb3e_b.jpg2021-01-15_08-28-35 by snub_you, on Flickr

https://live.staticflickr.com/65535/...32c4d0b0_b.jpg2021-01-15_08-28-42 by snub_you, on Flickr

SpongeG Mar 11, 2021 8:56 AM

drove past today, this is about 2 or 3 floors above ground now, starting to rise.

jaykk3 Mar 13, 2021 5:00 PM

Quote:

Originally Posted by SpongeG (Post 9214622)
drove past today, this is about 2 or 3 floors above ground now, starting to rise.

That’s exiciting. :notacrook:

officedweller Apr 24, 2021 1:19 AM

Scott Graham twitter April 17th:

https://pbs.twimg.com/media/EzNMsW5U...pg&name=medium
https://twitter.com/WFLBC

Klazu Apr 24, 2021 2:07 AM

I keep forgetting that there is a 50-floor tower rising here as well. Crazy how commonplace tall towers are becoming.

officedweller Apr 24, 2021 3:29 AM

I think these are the only renderings circulating (from Dec 2019):

https://images.dailyhive.com/2018022...oquitlam-3.jpg
https://dailyhive.com/vancouver/burq...ert-properties

https://images.dailyhive.com/2018022...oquitlam-7.jpg
https://dailyhive.com/vancouver/burq...ert-properties

https://images.dailyhive.com/2018022...oquitlam-6.jpg
https://dailyhive.com/vancouver/burq...ert-properties

https://images.dailyhive.com/2018022...oquitlam-5.jpg
https://dailyhive.com/vancouver/burq...ert-properties

https://images.dailyhive.com/2018022...oquitlam-2.jpg
https://dailyhive.com/vancouver/burq...ert-properties

https://images.dailyhive.com/2018022...oquitlam-f.jpg
https://dailyhive.com/vancouver/burq...ert-properties

officedweller Apr 24, 2021 3:40 AM

I think it's only the YMCA and the 33 storey rental tower under construction.

Can anyone confirm?

https://recollective.ca/wp-content/u...itlam-Park.png
https://recollective.ca/projects/burquitlam-park/

https://i.imgur.com/nN5LeGE.png
https://coquitlam.ca.granicus.com/Me...&meta_id=30517

invisibleairwaves Apr 24, 2021 8:17 AM

Yeah, the north end of the site (where the strata tower is going) is just being used for staging and site offices right now. Concert went back to council for a parking reduction a few months ago (the city had tweaked its policy after this project was initially approved), doesn't seem like there's been any movement since. Rental tower/YMCA are shooting up though. I'd grab some progress pics but my phone camera is...not great.


All times are GMT. The time now is 6:14 AM.